Consisting of 2 Stages, this project by GWH and was completed in early 2024.
Canavan Dr Beresfield
- 77 Tonnes of Structural Steel
- 2,200m of Purlins
- Structural Columns and Beams
- Mezzanine
- Stairs
Contact our specialised team for more information about our products and how we can meet your specifications.
Consisting of 2 Stages, this project by GWH and was completed in early 2024.
The large footprint meant a large span for the the structural steel roof and columns, designed and fabricated by Hunter Structural Steel. 23 tonnes of steel were used in the roof structure alone.